Two Argent Boulevard projects are moving at very different speeds. One is a set of new traffic signals, and two of them are already standing at their intersections. The other is a four-lane widening that Jasper County expects to begin building around 2030. For anyone in Sun City Hilton Head who uses Argent to get between US-278 and SC-170, the signals are what will change the drive this winter.
That order makes sense once you see the road. Argent is a two-lane, nearly 4-mile connector that drivers use to avoid McGarvey's Corner, the busy US-278 and SC-170 interchange. A 2023 traffic study counted upwards of 14,800 vehicles a day on Argent. For comparison, SCDOT counted 39,200 vehicles that year on the four-lane stretch of SC-170 from McGarvey's Corner to Lowcountry Drive. Argent carries a lot of traffic for a two-lane road, and most of the trouble happens where cars turn onto it or off it. So the signals come first.
Six signals, four of them new
The Island Packet's September 29 report on the widening plan described four new signals along the corridor. With the existing signals at East Argent and New River parkways and at the SC-170 end, that makes six in all. The two existing signals are already running. The four new ones are being installed, planned or bid.
| Intersection | Where it stands in mid-November 2026 | What comes next |
|---|---|---|
| US-278 and Argent Boulevard | Signal installed in June, turn lanes added July 27 | County lists substantial completion by November 30 |
| Short Cut Road and Jasper Station Road | Signal installed, waiting on the city's road realignment | Paving and striping targeted for November 30, signal by Christmas |
| Sundance Drive and Sgt. William Jasper Boulevard | Out to bid, with bids due December 3 | Construction expected to begin in early 2027 |
| Village Drive | Part of the widening plan | Built with the corridor project |
| East Argent and New River parkways | Existing signal | Stays |
| SC-170 terminus | Existing signal | Stays |
Each new signal has had its own holdup, so each is worth a short look.
US-278 starts with a flashing yellow
The US-278 end has always been controlled by a stop sign on Argent and a left-turn lane on the highway. Eastbound US-278 drivers cross two lanes of traffic to reach Argent. Drivers on Argent turning left onto eastbound US-278 have to wait for those cars to clear first, and the Island Packet reported in August that traffic backs up there often.
SCDOT put up the signal heads in June and kept them bagged while it worked on getting power to them. Dedicated turn lanes went in on July 27. Jasper County's transportation program lists November 30, 2026 as the date for substantial completion.
Here is the part that affects your drive. After SCDOT programs the timing, the light will run in a flashing-yellow pattern for a "short transition period" so drivers can get used to it. Full red, yellow and green operation follows. So for the first stretch after it's switched on, the light at Argent and US-278 may only be flashing.
Short Cut Road needed a new path before it could get a light
The signal at Short Cut Road and Jasper Station Road took longer for a basic reason. The two roads meet Argent at roughly the same spot without lining up with each other, and that offset kept SCDOT from installing a light. The City of Hardeeville started a $1.5 million project in 2025 that shifts Short Cut Road, which comes in from the east, slightly south so it lines up with Jasper Station Road.
Short Cut is itself a cut-through. Drivers on Argent and SC-170 use it in place of the Argent and SC-170 intersection half a mile away. That's why this intersection matters to so many people who have never looked up its name.
The city originally scheduled the work to finish in June 2026. Jodie McMahon, Hardeeville's Capital Improvement Program director, told the Island Packet in September that the project had "many elements of difficulty," including moving utility lines. That utility work has to pass inspection by the Beaufort-Jasper Water and Sewer Authority. If it does, paving and striping are set for November 30 and the lights for Christmas. The signal heads are already up and will stay dark until the city's work is done.
The utility work also links the two Argent projects. The county's transportation sales tax program is helping pay for the Short Cut utility relocation because the future widening would have required it anyway. In other words, part of the widening is already being paid for through this smaller intersection job.
The light at Sun City's own entrance comes next
The Island Packet called Sundance Drive and Sgt. William Jasper Boulevard "Sun City Hilton Head's intersection," and it's the third of the four new signals. Most of this year's attention to Sundance Drive has gone to the community's new western clubhouse. The entrance onto Argent is the piece still in progress.
SCDOT approved a signal there on February 13. At the time, the city said design, permitting and bidding still had to happen before construction. The project is now at the bidding stage. The City of Hardeeville's contract notice was published on November 6 in South Carolina Business Opportunities, with bids due December 3 at 2 p.m. The county expects construction to begin in early 2027.
So the light at Sun City's entrance trails the US-278 and Short Cut signals, but it's still years ahead of any new lane.
The lanes are a 2030s project
The widening grew quickly. In November 2025, Hardeeville City Manager Josh Gruber said the city had no plans to widen Argent itself. Ten months later, the Island Packet reported that a widening plan was underway. It's paid for by the county's "penny tax," the 1% sales tax Jasper County voters approved in 2024 for road improvements and greenbelt work. Argent is one of the first of 16 large projects on that list. The county has also secured $12 million in additional construction funding through the Lowcountry Council of Governments' Traffic Improvement Plan.
The plan presented this fall would add a 12-foot travel lane in each direction and a 10-foot shared-use path with curbing on both sides of the road. Where driveways face each other, a 15-foot center turn lane would separate traffic. Where there are no driveways, a raised grass median would. The Island Packet reported that the median would run mainly along the stretch next to Sun City Hilton Head's expansion.
The county is weighing two alignments:
- Center alignment keeps Argent's current centerline, so land would be needed on both sides of the road.
- Asymmetrical alignment shifts the road to reduce the effect on developed property. It would widen more to the north near US-278, then more to the south as the road passes Sun City Hilton Head toward SC-170.
Dozens of people filled the Palmetto Electric Cooperative community room in Hardeeville on October 1 for the public meeting, WTOC reported. Attendees asked about construction lighting and traffic noise after the project, and many property owners asked how close the road would come to their backyards. Jim Iwanicki, Jasper County's interim administrator and engineering services director, described where things stand:
"So it is a done deal that we will be improving Argent Boulevard. It isn't a done deal on how we are going to do it."
He said engineers would review the meeting's suggestions, including sound barrier walls, earthen berms and changes to turn lanes, as they refine the plans.
The county's project page lays out the schedule:
- Planning study and survey data collection, 2026
- Preliminary engineering and design, 2026 to 2027
- Environmental review, 2026 to 2028
- Right-of-way acquisition, 2028 to 2029
- Utility coordination, 2028 to 2030
- Construction, with an estimated start in 2030 or 2031 and estimated completion in 2035
Field work is underway now, including surveying, traffic counts and environmental assessment. That means you may see survey crews on Argent long before any construction equipment.
The speed limit waits for the lanes
The speed limits follow the widening schedule, not the signal schedule. Last year Hardeeville had SCDOT lower the limit from 55 mph to 45 mph on parts of Argent. The straight middle section had to stay at 55. The Island Packet reported that the current pattern of 45 mph at both ends and 55 in the middle stays in place until widening begins. Jasper County is expected to revisit a 45 mph limit for the whole widened section at that point.
For the next several years, the drive from Sun City keeps its two lanes and its 55 mph middle section. The US-278 and Short Cut Road signals are scheduled for this winter, Sundance Drive is expected to start construction in 2027, and the extra lanes come after 2030. For more on how growth around Exit 8 is changing the rest of the area, see our Hardeeville fall guide.
If you own a home near Argent and want to understand how the two proposed alignments and the corridor schedule could affect your street before you decide on a sale or a move, the team at Joan Kelly Group is glad to go over it with you. When you're ready, we can start with a free home valuation based on what's actually planned for the road.